There is exciting news to convey as we embark on week 3 of the Bridport Walking Track building experience. Team leaders Nick and Tim

Bridport Walking Track, Pierotti Bridport

Team Leaders- Nick and Tim- pleased with progress

report that 78 metres of base/top gravel has now been laid, and is ready for final compacting. Another 41 metres of base gravel is also ready for a top layer dressing.

The gravel, transported to the site by local contractors, has been obtained from special ‘track grade quarries’ in the area.

Approximately 119 metres of track  now weaves (with minimal impact) a path through a flourishing dry sclerophyll forest at the Maxwell St end of the Bridport Walking Track experience.

Bridport Walking Track, Pierotti Bridport

Base gravel on a curved creative path

Bridport Walking Track, Pierotti Bridport

Chewy on the path- introducing Chewy

Bridport Walking Track, Pierotti Bridport

Unloading dirt for replanting of native plants

The second team of 10 trainees begins work on track construction this week  where they will find track prepared for graveling and their finishing touches. They will proceed with the skills of track carving, cultivating and grooming as their ‘hands-on’ training is consolidated .

Bridport Walking Track, Pierotti Bridport

Virgin track construction

Bridport Walking Track, Pierotti Bridport

Loading top gravel- introducing Sam, Jess, Kathy

Bridport Walking Track, Pierotti Bridport

Grading work, top layer

The enthusiasm of the ‘handpicked’ trainees is infectious along with their pride in showing their finely honed track building achievements to the Program Manager, and other guests when they arrived on the site today.

Text and Photos: Judy Barnett